The National Hydroelectric Power Corporation (NHPC) today agreed to explore the scope of reducing the height of the dam of the Lower Subansiri Hydroelectric Power Project (LSHEP), considering the h

The projects are being developed by the central and state governments and also by the private sector

Over 14,000 MW of hydro power capacity is under execution in the country and would be commissioned in the next four years, according to the Central Electricity Authority (CEA).

ITANAGAR, March 25: The Lower Subansiri Hydro Electric Project under its Corporate Social Responsibility and Sustainable Development Scheme has partnered with Operation Smile, an International NGO

New Delhi, March 25: Term it a lackluster attitude being adopted by the two central ministries (Ministry of Environment and Forests, and Ministry of Power), their inability to submit report on the

THE empowered group of ministers (EGoM) for hydel power projects in Arunachal Pradesh will find it tough to get the ministry of environment and forests (MoEF) on board for the proposed all-at-a-time clearance mechanism for supporting infrastructure projects.

According to sources, at the upcoming EGoM meeting the power ministry will pitch for a simultaneous process for environmental and forest clearances as well as the approvals for land acquisition and preparation of detailed project reports (DPRs) for supporting infrastructure projects like roads and bridges.

Guwahati: The total cost of NHPC’S Subansiri project in Assam has gone up by about Rs 1,200 crore due to forced suspension of work since December 2011, following agitation by a section of stakehold

The National Green Tribunal (NGT) on Monday decried the Assam government after the latter failed to submit report on the 2000MW Lower Subansiri Hydro Power Project.

The Ministry of Environment and Forests and the Ministry of Power also failed to submit their reports when the tribunal took up the case for hearing.

Taking up the much controversial National Hydro Power Corporation (NHPC)’s 2,000MW Lower Subansiri Project case, the National Green Tribunal (NGT) on Wednesday asked the corporation, the government

The National Green Tribunal (NGT) on Monday accepted the petition filed by the Assam Public Works (APW), an NGO, on the 2000MW Lower Subansiri Hydro Power Project.

National Green Tribunal (NGT) on Monday admitted a case pertaining to the ecological issues related to the downstream of the Lower Subansiri Hydro Electric Project dam by the National Hydroelectric