Order of the National Green Tribunal in the matter of Abani Kumar Sahoo Vs State of Odisha & Others dated 04/08/2023.The matter related to illegal sand mining in Rayan Ramchandrapur Sand Source in an area of 20.38 acres. It is stated that the Tahasildar,Jaleswar executed a lease deed in favour of the miner on April 13, 2021.Environmental Clearance was also granted by the State Environment Impact Assessment Authority (SEIAA) Odisha, on July 13, 2017.

The order of the National Green Tribunal (Eastern Zone Bench) in the matter of Bibhindra Beura & Others Vs State of Odisha & Others dated 12/06/2023.

Grievance in the application is against setting up and operation of greenfield project of 125 KLD grain based ethanol plant along with 4 MW cogeneration power plant at village Banana, tehsil Dumpada, district Cuttack, Odisha by M/s. Cuttack Agrivet Private Limited.

Order of the National Green Tribunal in the matter of Wildlife Society of Orissa Vs State of Odisha & Others dated 14/03/2023.

The NGT, Eastern Bench, Kolkata expressed displeasure with the Principal Chief Conservator of Forests and Chief Wildlife Warden, Odisha at the lack of progress made in complying with the court order for notifying elephant corridors in the state.

Order of the National Green Tribunal in the matter of Rakesh K.V. Malik & Others Vs State of Odisha dated 03/03/2023.

Order of the National Green Tribunal in the matter of Srikanta Kumar Pakal & Others Vs State of Odisha & Others dated 09/01/2023.

The matter related to discharge of waste water by M/s. Hotel Presidency, Nayapalli, Bhubaneswar, Odisha.

The court noted that the test report of water samples of the hotel show high levels of biochemical oxygen demand (BOD), total suspended solids (TSS) as well as faecal coliform. However, these "two test reports do not give the standards/regulatory limits".

Report filed by the Office of the Collector and District Magistrate, Keonjhar on the operation of Kantipal Stone Quarry located in Anandapur tahasil, Kendujhar district, Odisha.

Order of the National Green Tribunal in the matter of Pratap Chandra Mohanty & Others dated 12/10/2022.

The applicants have said that the National Highway Authority of India (NHAI), engaged in the rehabilitation and upgradation of existing 2-lane to 4-lane standards from Duburi to Chandikhole section of NH-200 from 388.376 kilometers to 428.074 kilometers, length of 40 kilometers in the state of Odisha under the NHDP Phase-III on EPC Mode (Pkg-III) and the construction period of the said project is 910 days.

Order of the National Green Tribunal (Eastern Zone Bench, Kolkata) in the matter of Tribunal On its Own Motion Vs State of Odisha & Others dated 26/09/2022.

The Collector and District Magistrate-cum-Chairman, District Environment Impact Assessment Authority (DEIAA), Kendrapara has informed the NGT, Eastern Zone Bench, Kolkata that due to flood, the work of preservation of the embankment of Brahmani river and Mahanadi river could not be commenced.

Order of the National Green Tribunal (Eastern Zone Bench, Kolkata) in the matter of Ghanashyam Rout Vs State of Odisha & Others.

Order of the National Green Tribunal (Eastern Zone Bench, Kolkata) in the matter of Srikanta Kumar Pakal & Others Vs State of Odisha & Others dated 09/09/2022.