Kishenganga goes Baglihar way Huge delays, cost almost doubles up [1]

JAMMU, Nov 17: After Baglihar, the ambitious Kishenganga hydro project of J&K too is paying a heavy price for injudicious planning on the part of helmsmen as well as long standing dispute between India and Pakistan over water resources as the cost of this 330 mw project has escalated by 62.69 per cent to Rs. 3,642.04 Cr as against its original cost of Rs.

Publication Date: 
18/11/2010
Kashmir Times (Jammu) [2]
Tags:
Jammu & Kashmir [3], Hydroelectricity [4], Ministry of Statistics and Programme Implementation [5]
Centre for Science and Environment
National Knowledge Commission Government of India

Technology Partners: MimirTech


India Environment Portal by Centre for Science and Environment is licensed under a Creative Commons Attribution-Share Alike 2.5 India License.


Source URL: http://admin.indiaenvironmentportal.org.in/news/kishenganga-goes-baglihar-way-huge-delays-cost-almost-doubles

Links:
[1] http://admin.indiaenvironmentportal.org.in/news/kishenganga-goes-baglihar-way-huge-delays-cost-almost-doubles
[2] http://admin.indiaenvironmentportal.org.in/category/newspaper/kashmir-times-jammu
[3] http://admin.indiaenvironmentportal.org.in/category/thesaurus/jammu-kashmir
[4] http://admin.indiaenvironmentportal.org.in/category/thesaurus/hydroelectricity
[5] http://admin.indiaenvironmentportal.org.in/category/thesaurus/ministry-statistics-and-programme-implementation