Report of the Comptroller and Auditor General of India on Schemes for Flood Control and Flood Forecasting [1]

This audit report on “Schemes for Flood Control and Flood Forecasting” by the Comptroller And Auditor General of India (CAG), examined whether schemes for flood control and flood forecasting were efficient and effective. It revealed delays in completion of projects under the flood management programmes.

[2]The Performance Audit on “Schemes for Flood Control and Flood Forecasting” examined whether schemes for flood control and flood forecasting were efficient and effective; and whether the review and oversight mechanisms were effective. The Performance Audit showed that there were long delays in approval of Detailed Project Reports leading to technical designs becoming irrelevant at the time of actual funding. Flood management works were not taken up in an integrated manner covering entire river/tributary or a major segment of rivers/tributaries. There were delays in completion of the projects under Flood Management Programme. A large number of the telemetry stations installed during the XI plan remained non-functional, as such real time data for most of the period was not available. There were also huge delays in completion of all the projects under River Management Activities and Works related to Border Areas. Emergency Action Plans had been prepared for only a few large dams. Key recommendations of Rashtriya Barh Ayog such as scientific assessment of flood prone areas and enactment of Flood Plain Zoning Act have not materialised. Performance and concurrent evaluation was not done as per scheme guidelines.

Publication Date: 
21/07/2017
Comptroller and Auditor General of India [3]
Tags:
Flood Control [4], Finance [5], Comptroller and Auditor General of India (CAG) [6], India [7], Disaster Management [8], Floods [9]
Centre for Science and Environment
National Knowledge Commission Government of India

Technology Partners: MimirTech


India Environment Portal by Centre for Science and Environment is licensed under a Creative Commons Attribution-Share Alike 2.5 India License.


Source URL: http://admin.indiaenvironmentportal.org.in/reports-documents/report-comptroller-and-auditor-general-india-schemes-flood-control-and-flood

Links:
[1] http://admin.indiaenvironmentportal.org.in/reports-documents/report-comptroller-and-auditor-general-india-schemes-flood-control-and-flood
[2] http://indiaenvironmentportal.org.in/files/file/Performance_audit_Union_Government_Schemes_for_Flood_Control_and_Flood_Forecasting.pdf
[3] http://admin.indiaenvironmentportal.org.in/category/publisher/comptroller-and-auditor-general-india
[4] http://admin.indiaenvironmentportal.org.in/category/thesaurus/flood-control
[5] http://admin.indiaenvironmentportal.org.in/category/thesaurus/finance
[6] http://admin.indiaenvironmentportal.org.in/thesaurus/comptroller-and-auditor-general-india-cag
[7] http://admin.indiaenvironmentportal.org.in/category/thesaurus/india
[8] http://admin.indiaenvironmentportal.org.in/category/thesaurus/disaster-management
[9] http://admin.indiaenvironmentportal.org.in/category/thesaurus/floods