Tata's Mundra plant fully operational
Tata Power Co Ltd today fully synchronised the fifth and last unit of its ultra mega power project (UMPP) in Mundra, Gujarat, taking the project to its full capacity of 4,000 megawatts (Mw).
Four units of this UMPP--800 Mw each--were commissioned in a single year, which the company calls "a new record". The addition of one of the country's largest power projects into the portfolio takes the total generation capacity of Tata Power, the country's largest private power utility, to 8,500 Mw.