The High Court of Karnataka on Monday ordered status quo on the hydel power project of Maruthi Power Gen (India) Private Limited at Kagneri and Kenchankumari reserve forests of Sakaleshpur range in Hassan district.

The order came after a spot inspection revealed that the company had completed only 20 per cent of the work against its claim to have completed 70 per cent of the work.