Parwanoo-Shimla 4-laning project rejected last month
New NHAI guidelines delay work on road projects
New National Highway Authority of India (NHAI) guidelines making forest clearance and acquisition of minimum quantum of land mandatory before inviting bids is delaying road projects to be executed in the public-private partnership mode. As per the guidelines, a project will be cleared for tendering only after the authorities concerned complete the process of acquisition under Section 3(A) of the National Highways Act and acquire at least 60 per cent of the land under Section 3(D) of the Act.