Judgement of the National Green Tribunal regarding environment clearance and consent to establish granted to M/s. Lenzing Modi Fibre India Ltd., 28/11/2013

Judgement of the National Green Tribunal in the matter of Nicholas H. Almeida Vs M/s Lenzing Modi Fibres India Pvt. ltd. Ors. dated 28/11/2013 regarding environment clearance and consent to establish granted to M/s. Lenzing Modi Fibre India Ltd. who has proposed a project for manufacturing of Viscose Fibers (80,000 TPA) with Captive Power Plant (16 MW) at plot No.M-1, M-2 of Maharashtra Industrial Development Corporation (MIDC) Additional Patalganga Industrial Area, village Sarsai, Tqh. Panvel, District Raigad, Maharashtra.

Original Source: http://www.greentribunal.gov.in/judgment/170_2013(Ap)(WZ)_28Nov2013_final_order.pdf