Order of the National Green Tribunal regarding cutting of trees to construct a ramp as part of the PWD’s Elevated Corridor project between Vikaspuri and Mukarba Chowk, 18/06/2014

Order of the National Green Tribunal (Principal Bench, New Delhi) in the matter of Dr. P.C. Prasad Ors. Vs Govt. Of NCT of Delhi Ors. dated 18/06/2014 regarding cutting of trees to construct a ramp as part of the PWD’s Elevated Corridor project between Vikaspuri and Mukarba Chowk, 18/06/2014. The counsel appearing for Respondents has submitted that there were totally 5016 trees on the entire stratch of 14 kms from Vikas Puri to Mukarbachowk. Out of which total 1080 trees were cut at 3 stages for completion of the Project.

cut 206 trees to construct a ramp as part of the PWD’s Elevated Corridor project between Vikaspuri and Mukarba Chowk