Amendment to environment clearance order (11 June, 2010), under the provision of Environment Impact Assessment (EIA) Notification, 2006.

This press release by Paryavaran Suraksha Samiti expresses concern that the effluent treatment facilities across golden corridor does not conform to GPCB norms and demands that effluent discharge at Tadgam Sarigam Pipeline, from FETP, Ankleshwar, ECP, Vadodara and CETPs of Ahmedabad be stopped. <br>

Minutes of the 11th meeting of the Gujarat Coastal Zone Management Authority held on 10/03/2010.

Environment clearance for proposed project township and area development project at Survey No.151 (Part), Mundra, Kutch by M/s Adani Mundra SEZ Infrastructure Pvt Ltd (20 Feb, 2010).

Environment clearance for establishment of Common Effluent Treatment Plant (CETP) of 17 MLD capacity at Survey No.141 (Part), Mundra, Kutch by M/s MPSEZ Utilities Pvt Ltd (20/02/2010).

Effluent Conveyance System called as Effluent Channel Project (ECP) is provided to carry treated effluent from industries (mostly chemical) located near Vadodara to the Gulf of Cambey, Arabian Sea. The industries along the stretch in the area from Padra Taluka (Vadodara District) and Jambusar Taluka (Bharuch District) also join the ECP for effluent discharge.

Letter to MOEF by villagers against grant of environmental clearance to Cement Plant (Cement Plant 1.91 MTPA: 1.50 Clinkar), Coke Oven Plant (1.5 LTPA) and Captive Power Plant (50 MW) of M/s. Nirma Ltd, near Village Padhiyarka, Taluka Mahuva, District Bhavnagar, Gujarat.

This is an EIA report that Nirma Limited (NL) proposes to set up a cement plant (cement plant 1.91 million tonnes per annum (MTPA), 1.5 MTPA clinker), coke oven (capacity 1.5 Lakh TPA) and a captive power plant (capacity 50 MW) at village Padhiarka, 15 km from Taluka headquarters Mahuva in district Bhavnagar of Gujarat.

This is an executive summary of EIA & EMP that Nirma Limited (NL) proposes to set up a cement plant (cement plant 1.91 million tonnes per annum (MTPA), 1.5 MTPA clinker), coke oven (capacity 1.5 Lakh TPA) and a captive power plant (capacity 50 MW) at village Padhiarka, 15 km from Taluka headquarters Mahuva in district Bhavnagar of Gujarat.

Minutes of the 10th meeting of the Gujarat Coastal Zone Management Authority held on 22/04/2008.