Demands initiation of an independent safety review

The Coalition for Nuclear Disarmament and Peace (CNDP) has demanded an immediate halt to the commissioning of the Kudankulam nuclear power project (KKNPP) and initiation of an independent safety review.

An environmental group has filed a fresh petition in the Madras high court seeking review on clearance for first Approach to Criticality

The Atomic Energy Regulatory Board on Thursday granted its clearance for ‘first approach to criticality’ for the first unit of the Kudankulam Nuclear Power Project.

Reaffirming their commitment to the timely implementation of the civil nuclear cooperation agreement, India and the US are pushing the Nuclear Power Corporation of India (NPCIL) and Westinghouse to expedite their consultations for a plant.

India is planning to add 30,000 MW of nuclear generation in the public sector in the next 20 years, which means business worth $100 billion for reactor suppliers and civil construction firms.

The Indian government has announced that it plans to purchase six European Pressurised Reactors for Jaitapur from the French company, Areva. No EPR is in commercial operation anywhere else in the world. Estimates of costs from plants under construction in Finland and France suggest that each unit may cost as much as Rs 60,000 crore; at this price, six units will cost Rs 3.6 lakh crore. The paper shows that the expected starting tariff for electricity from these reactors, without including transmission and distribution costs, is likely to be around Rs 15 per unit (kWh).

The company is supposed to supply two reactors of 1,650 Mw each to the Nuclear Power Corporation (NPC) for Jaitapur

Areva, the Paris-based partner for the government in the Jaitapur nuclear power project in Maharashtra, has asked the French government and banks for help on cost-sharing.

They have intensified their cause to save the environment from effects of radioactivity.

A crucial investors’ meeting to underwrite the financial package for two 1,650 megawatt Areva EPR reactors to be built in Jaitapur, Maharashtra, got under way here with a top four-man team from Ind

Nuclear Power Corporation (NPC), Areva and French banks and financial institutions will negotiate terms and conditions to provide funds for the development of 9,900 MW Jaitapur nuclear power projec

Activists and experts under the platform of the Coalition for Nuclear Disarmament & Peace (CNDP) have termed the Supreme Court’s go-ahead to the controversial nuclear power plant at Kudankulam