Engineers involved in the East-West Metro project would rather miss the 2012 deadline than mess with the drainage pipes, electricity lines and telecom cables criss-crossing Salt Lake.
Sources in the Calcutta Metro Railway Corporation, which is overseeing the project, blamed the unavailability of maps of underground utilities for the delay in starting construction.